Planet Lean: The Official online magazine of the Lean Global Network
Stand there first

Stand there first

Daniel Halvarsson
April 21, 2026

MY AHA MOMENTS – Opening a reflective new series on his lean “aha” moments, the author recalls discovering the power of gemba observation to reveal hidden capacity without investment.


Words: Daniel Halvarsson


"We're talking about a lot of money. And the problem is that we need capacity now — not after six months of approvals and another year of installation," said the production manager, his frustration filling the stuffy meeting room. Around him sat production engineers and team leads from an ABB (now Hitachi Energy) high-voltage manufacturing facility in Sweden, all facing the same wall. Projected onto it was a sprawling Excel sheet, the draft business case for expanding the test cell, the most expensive station on the production floor. Cost estimates. Timelines. Milestones and capacity projections. I was in that room too, early in my career, and I remember staring at that spreadsheet with complete certainty that the answer was somewhere in its columns. The test cell was the bottleneck. We needed more capacity. The only question was how fast we could move the money.

I wasn't wrong about the urgency. Deliveries were slipping and customers were waiting. But I was wrong about the answer—and so was everyone else in that room. We never took the time to walk those 50 meters separating us from the production floor and the test room, to watch the actual work we were so busy trying to fund.

A week later, the same group gathered for an internal lean training session that had been organized earlier that year. The test cell bottleneck surfaced immediately. The frustration was fresh, the business case still grinding through its early stages. One of the production engineers began outlining the investment rationale, the numbers he and his colleagues had been refining all week.

In the corner sat a senior facilitator, a man who had been with the company long enough to have seen problems like this come and go. He listened quietly as the discussion built momentum. Then, without raising his voice, he pushed his chair back to the table and stood up. "Let's take a walk," he said.

No framework. No explanation of what we were about to do or why. Just an older man who had seen enough to know when a room full of people was focusing on the wrong thing.

Standing on the production floor, the constraint looked different than it did on the Excel sheet. The queue in front of the test cell was a forest of units packed so densely you could barely see through to the other side. And the pile kept growing, week by week, while the testers worked steadily inside. I had walked past this queue many times, but never stopped to look and try to understand why it was so big.

After a while, as we stood on that floor watching, one of the production engineers shifted his weight and checked his watch. "We should get back," he said. "We need to align and finalize those numbers." The production manager held up a hand. "Wait. There's something here."

And there was. The testers were spending a significant portion of their time inside the cell on preparation, connecting wires, arranging cables, configuring setups. All necessary steps. But not one of them was testing. The cell's most expensive resource was being consumed by work that didn't require it.

Finally, a production leader broke the silence, "Why can't we move that preparation outside the test room? Isn't that just waste?"

Someone pushed back: "It's not really waste. It's value-enabling." The production leader wasn't deterred. "Sure, but do we really have to do it inside the test room? I mean, does this require our highly trained testers?" The production manager nodded slowly. "You're right. Someone else can do that. And then we get much more through the test room."

The team spent the rest of that day observing, listing every step that wasn't pure value-adding work. They even ran an experiment: one tester prepared all cabling outside the cell beforehand. It worked. That single change freed roughly 30% of the time inside the cell. Within weeks, a standard procedure was in place. Effective testing capacity increased by 30 to 40%. No capital expenditure. No new equipment. The constraint that had justified a significant budget request dissolved because one man stood up from his chair and said, "Let's take a walk."

That was nearly two decades ago. Since then, I have worked with many different organizations across industries, and the pattern is always the same. Today we sit in Zoom meetings, where leadership teams discuss the fate of factories they visit once or twice a year. I watch production managers and line managers spend more hours in video calls at their desks than walking around on the floor they are responsible for. The distance between the decision-maker and the gemba is no longer fifty meters. It is a screen, a time zone, sometimes an ocean.

The most expensive decision in that room that day was the one we almost made without looking. And I worry that still today, in meeting rooms and on video calls in every type of industry, we are repeating the same mistake over and over again.


THE AUTHOR

Daniel Halvarsson is a lean coach based in Sweden

Read more

Getting started with lean process development
September 16, 2022
Getting started with lean process development

SERIES – In the final article in their series on lean process development, the authors discuss what it takes to get started with their 6CON process development model.

Continue reading
A people-centric lean HR strategy
June 20, 2019
A people-centric lean HR strategy

CASE STUDY – This automotive parts supplier based in southwest Spain is discovering the power of lean thinking applied to recruitment and Human Resources.

Continue reading
Lean project boosts sustainable development in Myanmar
September 1, 2016
Lean project boosts sustainable development in Myanmar

FEATURE – A group of Italian researchers and professionals partnered with a NGO to prove how lean thinking can pave the way for the competitiveness and sustainable development of SMEs in Myanmar. Is this a new model for the developing world?

Continue reading
Do you run a team or a gang?
August 27, 2020
Do you run a team or a gang?

FEATURE – The author discusses two ways in which people can work together in a group – a team or a gang – and explains why you will need both at one time or another in your lean transformation.

Continue reading

Read more

5 ways to improve your connection with the gemba
May 31, 2022
5 ways to improve your connection with the gemba

FEATURE – The author discusses the practices that can help us make the most of the traditional mantra “go see, ask why, and show respect”.

Continue reading
Enhancing your gemba skills
February 24, 2020
Enhancing your gemba skills

FEATURE – Michael Ballé shares a few tricks he uses to escape his default thinking and ensure he makes the most of every gemba walk he goes on.

Continue reading
How the gemba shaped my leader standard work
September 16, 2021
How the gemba shaped my leader standard work

FEATURE – Sharon Visser shares her leader’s standard work from when she ran the Ngami car dealership and encourages us to use what we see at gemba to shape our own.

Continue reading
Lean leadership means advocating problem solving at gemba
March 15, 2016
Lean leadership means advocating problem solving at gemba

PROFILE – It isn’t every day that you come across a hospital CEO coaching people on A3s and following his own standard work. So when you do, it’s important to share their story. This month we profile the CEO of a Brazilian cancer treatment center.

Continue reading